EUROPEAN JOURNAL OF OPERATIONAL RESEARCH
卷 239, 期 2, 页码 335-348出版社
ELSEVIER SCIENCE BV
DOI: 10.1016/j.ejor.2014.05.036
关键词
Project scheduling; Flexible profiles; Principal resources; Dependent resources; Discrete-time models
资金
- German Research Foundation (Deutsche Forschungsgemeinschaft, DFG) of the German government
This paper addresses the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP). Such a problem often arises in many real-world applications, in which the resource usage of an activity is not merely constant, but can be adjusted from period to period. The FRCPSP is, therefore, to simultaneously determine the start time, the resource profile, and the duration of each activity in order to minimize the makespan, subject to precedence relationships, limited availability of multiple resources, and restrictions on resource profiles. We propose four discrete-time model formulations and compare their model efficiency in terms of solution quality and computational times. Both preprocessing and priority-based heuristic methods are also applied to compute both upper and lower bounds of the makespan. Our comparative results show significant dominance of one of the models, the so-called variable-intensity-based model, in both solution quality and runtimes. (C) 2014 Elsevier B.V. All rights reserved.
作者
我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。
推荐
暂无数据