期刊
COMPUTERS & OPERATIONS RESEARCH
卷 39, 期 3, 页码 582-593出版社
PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.cor.2011.05.011
关键词
Scheduling; Batch-processing machine; Makespan (C-max); Ant colony optimization
This paper investigates the problem of minimizing makespan on a single batch-processing machine, and the machine can process multiple jobs simultaneously. Each job is characterized by release time, processing time, and job size. We established a mixed integer programming model and proposed a valid lower bound for this problem. By introducing a definition of waste and idle space (WIS), this problem is proven to be equivalent to minimizing the WIS for the schedule. Since the problem is NP-hard, we proposed a heuristic and an ant colony optimization (ACO) algorithm based on the theorems presented. A candidate list strategy and a new method to construct heuristic information were introduced for the ACO approach to achieve a satisfactory solution in a reasonable computational time. Through extensive computational experiments, appropriate ACO parameter values were chosen and the effectiveness of the proposed algorithms was evaluated by solution quality and run time. The results showed that the ACO algorithm combined with the candidate list was more robust and consistently outperformed genetic algorithm (GA), CPLEX, and the other two heuristics, especially for large job instances. (C) 2011 Elsevier Ltd. All rights reserved.
作者
我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。
推荐
暂无数据