A heuristic approach for resource constrained project scheduling with uncertain activity durations

期刊

COMPUTERS & OPERATIONS RESEARCH
卷 38, 期 9, 页码 1305-1318

出版社

PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.cor.2010.12.004

关键词

Resource constrained project scheduling; Random activity duration; Heuristic; Joint chance constraints programming

向作者/读者索取更多资源

In this paper, we address the resource constrained project scheduling problem with uncertain activity durations. Project activities are assumed to have known deterministic renewable resource requirements and uncertain durations, described by independent random variables with a known probability distribution function. To tackle the problem solution we propose a heuristic method which relies on a stage wise decomposition of the problem and on the use of joint probabilistic constraints. (C) 2010 Elsevier Ltd. All rights reserved.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据