4.2 Article

Project scheduling with inventory constraints

期刊

MATHEMATICAL METHODS OF OPERATIONS RESEARCH
卷 56, 期 3, 页码 513-533

出版社

PHYSICA-VERLAG GMBH & CO
DOI: 10.1007/s001860200251

关键词

project scheduling; temporal and resource constraints; inventories branch-and-bound

向作者/读者索取更多资源

Inventory constraints refer to so-called cumulative resources, which can store a single or several different products and have a prescribed minimum and maximum inventory, where the inventory is depleted and replenished over time. Some additional applications of cumulative resources, e.g. to investment projects, are also discussed in this paper. We study some properties of the feasible region of the project scheduling problem with inventory constraints and general temporal constraints and especially show how to resolve so-called resource conflicts. The feasible region represents the intersection of a union of polyhedral cones with the polyhedron of time-feasible solutions. These results can be exploited for constructing an efficient branch-and-bound algorithm which enumerates alternatives to avoid stock shortage and surplus by introducing precedence constraints between disjoint sets of events. Finally, we sketch how the procedure can be truncated to a filtered beam search heuristic. An experimental performance analysis shows that problem instances with 100 events and five cumulative resources can be solved in less than one minute.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.2
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据