Scenario-Based Proactive Robust Optimization for Critical-Chain Project Scheduling

出版社

ASCE-AMER SOC CIVIL ENGINEERS
DOI: 10.1061/(ASCE)CO.1943-7862.0001003

关键词

Scheduling; Duration; Robustness; Scenario; Critical-chain project management (CCPM); Cost and schedule

资金

  1. National Natural Science Foundation of China (NSFC) [70802045]

向作者/读者索取更多资源

The robustness of construction project schedules is a key factor that determines the capability of the schedules in offsetting the negative impact of uncertainties, which are the primary causes of project delays. This paper proposes a scenario-based proactive robustness optimization (SBPRO) method, which aims to improve the robustness of construction project schedules that are developed using the critical-chain project management (CCPM) method. The SBPRO method integrates scenarios that represent all possible situations that may happen during project implementation. Therefore, schedules are less sensitive to variations of situations than schedules developed using the traditional CCPM-based scheduling method. Moreover, the SBPRO method is based on a dual-objective function and optimizes schedules by balancing a trade-off between two objectives, namely, reducing the length of planned schedules and mitigating the uncertainties in schedule execution. The SBPRO method was validated in three case studies. The results showed that the SBPRO method outperformed the traditional CCPM-based scheduling method by generating schedules that could ensure higher probabilities of on-time project completion. The results also demonstrated that the SBPRO method could serve to promote the understanding and acceptance among project teams of the trade-off between project duration and schedule robustness when managing complex construction projects. (C) 2015 American Society of Civil Engineers.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据