Time-overrun factors in Nigerian construction industry

期刊

出版社

ASCE-AMER SOC CIVIL ENGINEERS
DOI: 10.1061/(ASCE)0733-9364(2001)127:5(419)

关键词

-

向作者/读者索取更多资源

Factors that affect time overrun in the Nigerian construction industry have been studied, and the rank agreement factor for the professionals are architects/engineers, 0.75; architects/builders, 0.83; quantity surveyors/engineers, 0.74; quantity surveyors/builders, 0.79; and engineers/builders, 0.69. Important findings are (1) the degree of occurrence of time overrun is high-between 80 and 90%; (2) relative contributions of the client, contractor, and others are 62, 32, and 6%, respectively; (3) time overrun is more pronounced in government/public sector projects (89%); and (4) time overrun occurs on all projects, irrespective of size.