4.7 Article Proceedings Paper

Fuzzy temporal characteristics of operations for project management on the network models basis

期刊

EUROPEAN JOURNAL OF OPERATIONAL RESEARCH
卷 147, 期 2, 页码 253-265

出版社

ELSEVIER
DOI: 10.1016/S0377-2217(02)00559-3

关键词

project management; operations analysis; fuzzy set; temporal characteristics; graph decomposition

向作者/读者索取更多资源

The temporal aspects of operations management under fuzzy durations are investigated. It is proposed the models of fuzzy temporal characteristics of operations on the basis of direct application of the extension principle of Zadeh to the critical path method. Method of computing of the fuzzy time windows for floats and the latest start and completion of operations on the basis of graph decomposition is represented. The method is demonstrated by an example problem. (C) 2002 Published by Elsevier Science B.V.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据