期刊
COMPUTERS & CHEMICAL ENGINEERING
卷 28, 期 12, 页码 2823-2835出版社
PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.compchemeng.2004.08.031
关键词
scheduling; production planning; steelmaking
In this paper we describe an optimization procedure for planning the production of steel ingots in a steel making-continuous casting plant. The strict requirements of the production process defeated most of the earlier approaches to steelmaking-continuous casting production scheduling. mainly due to the lack of information in the optimization models. Our formulation of the problem is based on the alternative graph, which is a generalization of the disjunctive graph of Roy and Sussman. The alternative graph formulation allow us to describe in detail all the constraints that are relevant for the scheduling problem. We then solve the problem by using a beam search procedure, and compare our results with a lower bound of the optimal solutions and with the actual performance obtained in the plant. Computational experience shows the effectiveness of this approach. (C) 2004 Elsevier Ltd. All rights reserved.
作者
我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。
推荐
暂无数据