Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment

期刊

ANNALS OF OPERATIONS RESEARCH
卷 213, 期 1, 页码 271-291

出版社

SPRINGER
DOI: 10.1007/s10479-012-1277-0

关键词

Railway scheduling; Roadrunner scheduling; Feeding buffer; Priority list; Resource availability

资金

  1. China Scholarship Council
  2. National Natural Science Foundation of China [71201119, 71271097]

向作者/读者索取更多资源

The Critical Chain Scheduling and Buffer Management (CC/BM) methodology, proposed by Goldratt (Critical chain, 1997), introduced the concepts of feeding buffers, project buffers and resource buffers as well as the roadrunner mentality. This last concept, in which activities are started as soon as possible, was introduced in order to speed up projects by taking advantage of predecessors finishing early. Later on, the railway scheduling concept of never starting activities earlier than planned was introduced as a way to increase the stability of the project, typically at the cost of an increase in the expected project makespan. In this paper, we will indicate a realistic situation in which railway scheduling improves both the stability and the expected project makespan over roadrunner scheduling.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.6
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据