4.7 Article

Prediction of tunnel lining loads using correction factors

期刊

ENGINEERING GEOLOGY
卷 85, 期 3-4, 页码 302-312

出版社

ELSEVIER
DOI: 10.1016/j.enggeo.2006.03.001

关键词

tunnel lining loads; support delay factor; yield factor; prediction of lining loads; field measurements

向作者/读者索取更多资源

A design method for the prediction of lining loads should include the decrease of lining loads due to the stress release before lining installation and the increase of lining loads due to development of ground yielding. Schwartz and Einstein included both factors in their original closed form solutions in the form of a support delay factor lambda(d) and a yield factor lambda(y) respectively. The validity of the design method is reviewed by comparing the loads calculated using the methods with the field measurements obtained from several tunnels. The possible causes of the load discrepancy between measurements and predictions are presented. Schwartz and Einstein's proposed method gives reasonable results for tunnels with short delay lengths. However, the method could not be used reliably for tunnels either with long delay lengths or with voids between the soil and TBM due to the difficulties finding the pre-support ground movements and therefore lambda(d). (c) 2006 Elsevier B.V. All rights reserved.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据