4.5 Article

EDM: Earned Duration Management, a new approach to schedule performance management and measurement

期刊

INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT
卷 32, 期 6, 页码 1019-1041

出版社

ELSEVIER SCI LTD
DOI: 10.1016/j.ijproman.2013.11.002

关键词

Earned Value; EVM; Earned Schedule; Earned Duration; Earned Duration Management; EDM; Schedule management; Monitoring and control; Efficiency; Performance measurement; Forecasting; Estimation index; Performance and progress index; Project management

向作者/读者索取更多资源

The concept of schedule monitoring and control as one of the most important functions of project and program management has not been fully exploited. One possible explanation could be the dominance of the Earned Value Management System (EVMS, also known as EVM). EVM was originally developed as a cost management and control tool which was extended to track the schedule as well. EVM and its derivatives (e.g. Earned Schedule) use cost as a proxy to measure schedule performance to control the duration of the project. While there is a correlation between schedule, cost, quality, and scope of a project, using cost to control duration has proven to be misleading. In contrast to Earned Value and Earned Schedule, the authors have developed the Earned Duration Management (EDM) in which they have decoupled schedule and cost performance measures and developed a number of indices to measure progress and performance of schedule and cost, as well as the efficacy and efficiency of the plan at any level of the project. These new indices are easy to understand, have wider applications, and can be used by contractors, clients and the scheduling offices to assess and measure schedule performance. The newly developed duration performance measures are all schedule-based and can be used for forecasting the finish date of the project. (C) 2013 Elsevier Ltd. APM and IPMA. All rights reserved.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据