A mixed-integer linear programming model for integrated production and preventive maintenance scheduling in the capital goods industry

期刊

出版社

TAYLOR & FRANCIS LTD
DOI: 10.1080/00207543.2018.1459923

关键词

manufacturing and maintenance; integrated scheduling; capital goods; mixed integer linear programming

资金

  1. Thailand Research Fund [PHD/0135/2552]

向作者/读者索取更多资源

The scheduling literature is extensive, but much of this work is theoretical and does not capture the complexity of real world systems. Capital goods companies produce products with deep and complex product structures, each of which requires the coordination of jobbing, batch, flow and assembly processes. Many components require numerous operations on multiple machines. Integrated scheduling problems simultaneously consider two or more simultaneous decisions. Previous production scheduling research in the capital goods industry has neglected maintenance scheduling and used metaheuristics with stochastic search that cannot guarantee an optimal solution. This paper presents a novel mixed integer linear programming model for simultaneously solving the integrated production and preventive maintenance scheduling problem in the capital goods industry, which was tested using data from a collaborating company. The objective was to minimise total costs including: tardiness and earliness penalty costs; component and assembly holding costs; preventive maintenance costs; and set-up, production, transfer and production idle time costs. Thus, the objective function and problem formulation were more extensive than previous research. The tool was successfully tested using data obtained from a collaborating company. It was found that the company's total cost could be reduced by up to 63.5%.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据