Factors Affecting Rework Costs in Construction

出版社

ASCE-AMER SOC CIVIL ENGINEERS
DOI: 10.1061/(ASCE)CO.1943-7862.0001324

关键词

Rework costs; Project characteristics; Construction; Regression model; Cost and schedule

向作者/读者索取更多资源

Rework adversely impacts the performance of building projects. In this study, data were analyzed from 788 construction incidents in 40 Spanish building projects to determine the effects of project and managerial characteristics on rework costs. Finally, regression analysis was used to understand the relationships among contributing factors and to develop a model for rework prediction. Interestingly, the rework prediction model showed that only the original contract value (OCV) and the project location in relation to the company's headquarters contributed to the regression model. Project type, type of organization, type of contract, and original contract duration (OCD), which represents the magnitude and complexity of a project, were represented by the OCV. This model for rework prediction based on original project conditions enables strategies to be put in place prior to the start of construction, to minimize uncertainties, to reduce impacts on project cost and schedule, and, thus, to improve productivity. (C) 2017 American Society of Civil Engineers.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.6
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据