The Effect of Lead-Time Weather Forecast Uncertainty on Outage Prediction Modeling

期刊

FORECASTING
卷 3, 期 3, 页码 501-516

出版社

MDPI
DOI: 10.3390/forecast3030031

关键词

forecast uncertainty; lead time; severe weather; machine learning; power outages

资金

  1. DTN LLC
  2. Eversource

向作者/读者索取更多资源

The study indicates that weather parameter uncertainties, specifically precipitation and wind-gust variables, play a significant role in outage prediction errors. The dependence of outage prediction uncertainty on lead times is lower up to 3 days, with a stepwise increase at four- and five-day lead times.
Weather-related power outages affect millions of utility customers every year. Predicting storm outages with lead times of up to five days could help utilities to allocate crews and resources and devise cost-effective restoration plans that meet the strict time and efficiency requirements imposed by regulatory authorities. In this study, we construct a numerical experiment to evaluate how weather parameter uncertainty, based on weather forecasts with one to five days of lead time, propagates into outage prediction error. We apply a machine-learning-based outage prediction model on storm-caused outage events that occurred between 2016 and 2019 in the northeastern United States. The model predictions, fed by weather analysis and other environmental parameters including land cover, tree canopy, vegetation characteristics, and utility infrastructure variables exhibited a mean absolute percentage error of 38%, Nash-Sutcliffe efficiency of 0.54, and normalized centered root mean square error of 68%. Our numerical experiment demonstrated that uncertainties of precipitation and wind-gust variables play a significant role in the outage prediction uncertainty while sustained wind and temperature parameters play a less important role. We showed that, while the overall weather forecast uncertainty increases gradually with lead time, the corresponding outage prediction uncertainty exhibited a lower dependence on lead times up to 3 days and a stepwise increase in the four- and five-day lead times.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

3.9
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据