Robust long-term aircraft heavy maintenance check scheduling optimization under uncertainty

期刊

COMPUTERS & OPERATIONS RESEARCH
卷 141, 期 -, 页码 -

出版社

PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.cor.2021.105667

关键词

Scheduling; Min-max optimization; Genetic algorithm; Robustness optimization; Aircraft maintenance

向作者/读者索取更多资源

This paper applies a genetic algorithm to generate robust and efficient aircraft heavy maintenance check schedules, reducing workload and the need for frequent adjustments while considering uncertainties. A case study of a major European airline shows that the algorithm can find suitable maintenance schedules for a fleet of 45 aircraft in a short amount of time, reducing the total number of checks and increasing utilization.
Long-term heavy maintenance check schedules are crucial in the aviation industry since airlines need them to prepare the required maintenance tools, workforce, and aircraft spare parts. However, most airlines adopt a manual approach to plan the heavy maintenance check schedules in current practice. This manual process relies on the experience of their maintenance planners, and the resulting heavy maintenance schedules need frequent adjustment because of uncertainty. This paper applies a genetic algorithm (GA) to generate robust aircraft heavy maintenance check schedules. It aims to reduce the workload and the frequency of revising heavy maintenance schedules considering uncertainties associated with heavy maintenance check duration and aircraft daily utilization. A major European airline case study shows that the GA finds robust and efficient multi-year aircraft heavy maintenance schedules for a fleet of 45 aircraft in 30 min. Compared with the current approach followed by the airline, the algorithm reduces the total number of heavy maintenance checks by 7% while increasing utilization by 4.4%, which could potentially lead to a reduction of direct annual maintenance costs between $122.5K and $612.5K. Furthermore, when testing the robustness of the 4-years maintenance check schedules produced, a Monte Carlo analysis has shown that all aircraft could be maintained before their check due date for 41% of the episodes simulated, compared to 0.27% of the episodes for the single deterministic scenario approach.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据