This study introduces a new cost model for OWF decommissioning, which estimates the costs of removal and transportation phases using a bottom-up approach, and further estimates the overall decommissioning costs through project percentage breakdown analysis. The research findings demonstrate that the proposed cost model efficiently estimates the removal and transportation costs, and can be adapted to estimate the overall decommissioning costs.
The lifespan for offshore wind farms (OWFs) is between 20 and 25 years, and with a growing demand for renewable energy, the number of OWFs approaching decommissioning phase will dramatically increase in the coming years. This paper presents a new cost model by adopting a bottom-up approach for the removal and transportation phases of OWF decommissioning projects. Based on the experience in Oil and Gas industry, a project percentage breakdown analysis is also performed to expand the model further and estimate the overall decommissioning costs. To test the efficiency of the proposed cost modelling approach, the cost estimations for four OWF decommissioning case studies with different levels of public information and data are investigated. The numerical results revealed that in addition to the proposed cost model efficiently estimating the removal and transportation costs, it can also be adapted to estimate the overall decommissioning costs, by applying percentage weightages obtained from the percentage breakdown analysis.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据