4.7 Article

Monitoring a deep excavation in pyroclastic soil and soft rock

期刊

出版社

PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.tust.2021.104130

关键词

Excavation; Top-down procedure; Artificial ground freezing; Monitoring displacement; Groundwater table

向作者/读者索取更多资源

This study presents the construction process and monitoring results of the completion of the downtown stretch of Line 1 of the Napoli underground in Italy. It covers measurements of pore water pressures, displacement of retaining structures, ground anchor forces, temperature measurements, and subsidence of surrounding buildings. Valuable lessons are learned from the effectiveness of construction techniques and the relationships among different sets of measurements.
The completion of the downtown stretch of Line 1 of the Napoli (Italy) underground involved the construction of a number of stations in the historic centre of the city, including the Universit`a station. This station consists of two shafts excavated with the protection of reinforced concrete diaphragms, and two platform tunnels. The main shaft reaches the line tunnels excavated with TBMs in the formation of the Neapolitan Yellow Tuff, at a depth of more than 36 m below ground level and more than 33 m below the groundwater table; excavations of the shaft involved loose materials for a depth of 23 m, and the Neapolitan Yellow Tuff formation for the remaining. The two platform tunnels, each of them consisting in two separate stretches about 50 m long, were excavated from the main shaft using the Artificial Ground Freezing technique to guarantee excavation stability and hydraulic seal. The paper presents the main results of the monitoring carried out along the whole complex construction process for a total duration of about seven years; the presented data consists of: measurements of pore water pressures inside and outside the excavations; measurements of displacement of retaining structures and ground anchors forces; temperature measurements in the vicinity of the freezing probes around the tunnels excavation to check the frozen ring formation; measurements of subsidence of surrounding buildings. The case history is a very complete one and valuable lessons are learnt on the effectiveness of the construction techniques further than on the design methodologies adopted. Qualitative and quantitative relationships among the various sets of measurements are also outlined, such an aspect representing a valuable feature of the presented case history.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文