4.6 Article Retracted Publication

被撤回的出版物: Numerical simulation and analysis of the three-step excavation of an extra-large cross section and a low flat-ratio railway tunnel (Retracted article. See DEC, 2022)

期刊

SOFT COMPUTING
卷 25, 期 18, 页码 12117-12130

出版社

SPRINGER
DOI: 10.1007/s00500-021-05862-7

关键词

Extra-large section tunnel; Three-step method; Finite element analysis; Middle pipe shed; Excavation and tunneling

向作者/读者索取更多资源

This paper mainly describes the finite element analysis conducted for the Xinbaishiyan tunnel in the reconstruction Chengdu-Kunming railway, which was used to guide its construction. The analysis results showed the deformation of the tunnel during excavation, and discussed the construction of tunnels with extra-large cross sections.
The Xinbaishiyan tunnel in the reconstruction Chengdu-Kunming railway Ermeishan-Mipan section mainly runs through dolomite with dolomitic limestone, with an excavation area of 260 m(2), a maximum span of 22.3 m, a maximum height of 14.4 m, a vector height of 7 m, and a rise-span ratio of 0.31. The tunnel has an extra-large cross section, and it is a low flat-ration railway tunnel. This paper mainly describes the finite element analysis for this tunnel excavation that was used to guide the construction. Finite element software was used to model the tunnel according to the engineering geological conditions of the tunnel. These engineering geological conditions included the rock mass, system bolts, middle pipe shed, steel arch and shotcrete, grouting layer, second lining and so on. Nonlinear construction phase analysis was adopted. The results showed that the maximum vertical deformation of the tunnel vault and the middle of the invert was about 34 mm. The vertical deformation of the tunnel could be divided into an acceleration deformation section, linear deformation section, deceleration deformation section, and stable deformation section. The maximum horizontal deformation in the middle of the side wall was about 12.3 mm. Under the effect of the initial support, the equivalent stress of the side wall gradually increased with the excavation of the steps and the increase in the support structure. The axial force of the bolt in the middle of the side wall was larger than that in other places and the axial force of the middle pipe shed went along with the excavation of the tunnel in waves. The steel arch and the shotcrete had the maximum effective stress at the arch shoulder, which played the role of the deformation and pressure for the surrounding rock. During the construction, the length and height of the three-step method had to be set reasonably. The middle pipe shed and the system bolt supported the rock mass together. In the construction of the extra-large cross section and the flat tunnel, there was no need to set up temporary support, which was convenient for mechanical excavation.