The combined impact of stochastic and correlated activity durations and design uncertainty on project plans

期刊

出版社

ELSEVIER
DOI: 10.1016/j.ijpe.2020.108015

关键词

Project planning; Design uncertainty; Correlations; Flexibility; Learning behaviour

资金

  1. Research Council of Norway [280536]

向作者/读者索取更多资源

The study reveals that when modeling design uncertainty with multiple alternatives and delaying decisions on the final alternative, the impact of stochastic and correlated activity durations is limited. In situations where alternative and substitutable solutions are available for a given design, correlations drive certain learning behaviors.
Most model based studies on project uncertainty investigate a single source of uncertainty, with a dominant focus on stochastic activity durations. However, another major uncertainty facing engineering projects is that of changes in design troughout the project delivery. This may come from uncertainty in the market, technology, or regulations, leading to changes in design and implementation paths, with alterations in the project network itself. This comes on top of stochastic and correlated activity durations for a given design. In this paper we develop a stochastic program to investigate how uncertainty in design and activity durations, together, affect planning, and their relationships. The findings suggest that when design uncertainty is modelled by multiple alternatives and delayed decisions on the final alternative, stochastic and correlated activity durations have limited impact. In situations with alternative and subtitutable solutions available for a given design, correlations drive a certain learning behaviour.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.6
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据