BIM Adoption and Its Impact on Planning and Scheduling Influencing Mega Plan Projects- (CPEC-) Quantitative Approach

期刊

COMPLEXITY
卷 2021, 期 -, 页码 -

出版社

WILEY-HINDAWI
DOI: 10.1155/2021/8818296

关键词

-

资金

  1. China Scholarship Council of Zhejiang University
  2. National Natural Science Foundation of China [71971196]

向作者/读者索取更多资源

Construction projects in Pakistan face challenges with erroneous planning and scheduling, with limited focus on 2D CAD drawings interpretation problems and the role of BIM in efficient planning. This study highlights the positive impact of BIM on effective planning and scheduling in the Pakistani construction industry.
The construction projects in Pakistan have inherent problems of erroneous planning and schedule development. This dilemma has led to the failure of the majority of construction projects in Pakistan. Earlier researches have tried to curtail the increasing spectrum of inaccurate planning and schedule development. But not many research studies have shed light on the major factor of 2D CAD drawings interpretation problems, which are playing a key role in defective planning and scheduling. Moreover, the role of BIM, i.e., Building Information Modeling with respect to efficient planning, has not been also discussed in detail. This study has concluded a positive impact of BIM on effective planning and scheduling in the construction industry of Pakistan. About 210 responses were obtained from experienced construction professionals of Pakistan and tested via regression analysis in order to validate this argument. It has been analyzed that 2D CAD drawings are now getting primitive and 3D technology BIM is taking its place. BIM is an efficient tool for planning and scheduling. With the start of CPEC and Multi-Billion Dollar investment on infrastructure, construction industry of Pakistan needs to uplift its existing standard in order to meet with international requirements. For this purpose, BIM has been recommended. It will not only assist in attaining flawless planning but will also increase the success rate of CPEC projects in Pakistan.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据