4.8 Article

Risk-Constrained Day-Ahead Scheduling for Concentrating Solar Power Plants With Demand Response Using Info-Gap Theory

期刊

IEEE TRANSACTIONS ON INDUSTRIAL INFORMATICS
卷 15, 期 10, 页码 5475-5488

出版社

IEEE-INST ELECTRICAL ELECTRONICS ENGINEERS INC
DOI: 10.1109/TII.2019.2899003

关键词

Job shop scheduling; Uncertainty; Power generation; Load management; Load modeling; Concentrating solar power plant (CSPP); demand response (DR); information gap decision theory (IGDT); risk management; virtual power plant (VPP)

资金

  1. National Key R&D Program of China [2016YFB0901100]
  2. National Natural Science Foundation of China [51777185]

向作者/读者索取更多资源

The emerging concentrating solar power plant (CSPP) represents one of the promising technologies for promoting solar power applications. In this paper, risk-constrained day-ahead scheduling strategies for a virtual power plant (VPP) integrating a CSPP with some responsive residential and industrial loads are proposed considering the uncertainties from electricity price, thermal production of the solar field of the CSPP, and participation factor of residential demand response. The well-established information gap decision theory (IGDT) is utilized to hedge against the risk caused by these uncertainties. Based on IGDT, both a robust scheduling strategy for the risk-aversion decision maker and an opportunistic scheduling strategy for the opportunity-seeking decision maker are presented for hedging the profit risk of the VPP against variations of electricity price, thermal production, and demand response. Simulation results show that the presented IGDT-based method can act as an effective tool for managing risks from uncertainties, and also demonstrate that the RA VPP should focus more on the thermal production of the CSPP so as to guarantee the desired profit, whereas the OS VPP should pay more attention to the market price so as to achieve a windfall profit.