Probabilistic assessment of tunnel construction performance based on data

期刊

出版社

PERGAMON-ELSEVIER SCIENCE LTD
DOI: 10.1016/j.tust.2013.02.006

关键词

Construction time; Tunnel construction risk; Dynamic Bayesian Networks; Tunneling performance; Failure rate

资金

  1. Technology Agency of the Czech Republic [TA01030245]
  2. (CIDEAS research center) of the Ministry of Education, Youth and Sports of the Czech Republic [1M0579]
  3. DAAD
  4. Bayhost

向作者/读者索取更多资源

A probabilistic model for estimating tunnel construction time is learnt with data from past tunnel projects. The model is based on the Dynamic Bayesian Network technique. The model inputs are determined through an analysis of data from three tunnels built by means of the conventional tunneling method. The data motivate the development of a novel probability distribution to describe the excavation performance. In addition, the probability of construction failure events and the delay caused by such failures are estimated using databases available in the literature. The model is applied to a case study, in which it is demonstrated how observations from the tunnel construction process can be included to continuously update the prediction of construction time. (C) 2013 Elsevier Ltd. All rights reserved.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据