Determining the Probability of Project Cost Overruns

期刊

出版社

ASCE-AMER SOC CIVIL ENGINEERS
DOI: 10.1061/(ASCE)CO.1943-7862.0000575

关键词

Australia; Cost overrun; Distribution fitting; Probability; Probability distribution

向作者/读者索取更多资源

The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.5
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据