Rescheduling with controllable processing times for number of disrupted jobs and manufacturing cost objectives

期刊

INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH
卷 53, 期 9, 页码 2751-2770

出版社

TAYLOR & FRANCIS LTD
DOI: 10.1080/00207543.2014.980452

关键词

neighbourhood search; manufacturing cost; second-order cone programming; controllable processing times; rescheduling

向作者/读者索取更多资源

We consider a machine rescheduling problem that arises when a disruption such as machine breakdown occurs to a given schedule. Machine unavailability due to a breakdown requires repairing the schedule as the original schedule becomes infeasible. When repairing a disrupted schedule a desirable goal is to complete each disrupted job on time, i.e. not later than the planned completion time in the original schedule. We consider the case where processing times of jobs are controllable and compressing the processing time of a job requires extra processing cost. Usually, there exists a nonlinear relation between the processing time and manufacturing cost. We solve a bicriteria rescheduling problem that trades off the number of on-time jobs and manufacturing cost objectives. We give a mixed-integer second-order cone programming formulation for the problem. We develop a heuristic search algorithm to generate efficient solutions for the problem. Heuristic algorithm searches solution space by moving and swapping jobs among machines. We develop cost change estimates for job moves and swaps so that the heuristic implements only promising moves and hence generates a set of efficient solutions in reasonably short CPU times.

作者

我是这篇论文的作者
点击您的名字以认领此论文并将其添加到您的个人资料中。

评论

主要评分

4.7
评分不足

次要评分

新颖性
-
重要性
-
科学严谨性
-
评价这篇论文

推荐

暂无数据
暂无数据