Improving project cost estimation by taking into account managerial flexibility

Journal

EUROPEAN JOURNAL OF OPERATIONAL RESEARCH
Volume 127, Issue 2, Pages 239-251

Publisher

ELSEVIER SCIENCE BV
DOI: 10.1016/S0377-2217(99)00484-1

Keywords

project management; time-cost trade-off; stochastic dynamic scheduling

Ask authors/readers for more resources

Project costs tend to be higher than depicted by budgets. Irrespective of the quality of the project management, this indicates that the budgets are not established in a way which is consistent with how projects are run. Good budgets should on average lead to zero cost overruns. The purpose of this paper is to discuss how project costs (if they are based on models) can be better estimated by taking into account how projects are actually run, in particular, how managerial flexibility adds value to a project. The purpose is not to advocate better ways of running a project, but to obtain better estimates of what projects cost, given the way they are run. (C) 2000 Elsevier Science B.V. All rights reserved.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available