Heuristic scheduling of parallel machines with sequence-dependent set-up times

Journal

INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH
Volume 39, Issue 16, Pages 3747-3769

Publisher

TAYLOR & FRANCIS LTD
DOI: 10.1080/00207540110064938

Keywords

-

Ask authors/readers for more resources

In many manufacturing environments, multiple processing stations are used in parallel to obtain adequate capacity. Likewise, in many production environments, set-up activities are required for switching between items. This work addresses scheduling in parallel machines with sequence dependent set-up times and possibly non-zero ready times with the goal of minimizing makespan. Non-zero ready times allow for application in a continuous planning environment and will also support the expansion of the current model to a multistage production environment. An integer programming formulation is presented. Several heuristics, including approaches based on MULTI-FIT, genetic algorithms and the travelling salesman problem, are then developed and compared empirically. Seven factors are identified in order to generate problem data, including the number of parallel machines, the average number of jobs per machine, set-up time distribution parameters and processing time distribution parameters. The set-up time matrix can be either symmetric or asymmetric but must satisfy the triangle inequality. A modified insertion heuristic is found to perform best for these types of problems.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available