4.6 Article

Predetermined intervals for start times of activities in the stochastic project scheduling problem

Journal

ANNALS OF OPERATIONS RESEARCH
Volume 186, Issue 1, Pages 429-442

Publisher

SPRINGER
DOI: 10.1007/s10479-010-0733-y

Keywords

Stochastic project scheduling problem; Cross-entropy; Intervals; Gates; Flexible commitment

Ask authors/readers for more resources

This paper proposes a new methodology to schedule activities in projects with stochastic activity durations. The main idea is to determine for each activity an interval in which the activity is allowed to start its processing. Deviations from these intervals result in penalty costs. We employ the Cross-Entropy methodology to set the intervals so as to minimize the sum of the expected penalty costs. The paper describes the implementation of the method, compares its results to other heuristic methods and provides some insights towards actual applications.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.6
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available