THE TIME-COST TRADE-OFF ANALYSIS IN CONSTRUCTION PROJECT USING COMPUTER SIMULATION AND INTERACTIVE PROCEDURE

Journal

TECHNOLOGICAL AND ECONOMIC DEVELOPMENT OF ECONOMY
Volume 15, Issue 4, Pages 523-539

Publisher

VILNIUS GEDIMINAS TECH UNIV
DOI: 10.3846/1392-8619.2009.15.523-539

Keywords

project planning; multi-criteria decision aiding; time-cost trade-off; interactive approach; simulation

Categories

Ask authors/readers for more resources

Several criteria must be considered while preparing the schedule of a construction project. The completion time and project cost are analyzed in most cases. Additionally, the risk related to the criteria has to be taken into account as well. Thus, project planning problem can be defined as a multicriteria decision problem under risk. In this paper, a project scheduling problem including time-cost trade-offs is analyzed. We assume that various resource allocations can be considered. A new technique based on computer simulation and interactive approach is proposed. In the first step, simulation experiments are performed to evaluate decision alternatives with respect to the criteria. An interactive technique INSDECM is employed for generating the final solution of the problem. The procedure uses stochastic dominance rules for comparing decision alternatives with respect to the criteria. A numerical example is presented to illustrate the applicability of the technique.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.6
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available