4.5 Article

Optimal Scheduling of a Microgrid Including Pump Scheduling and Network Constraints

Journal

COMPLEXITY
Volume -, Issue -, Pages -

Publisher

WILEY-HINDAWI
DOI: 10.1155/2018/9842025

Keywords

-

Funding

  1. NTU Start-Up Grant
  2. International Center of Energy Research (ICER)
  3. Technische Universitat Munchen (TUM), Germany

Ask authors/readers for more resources

This paper proposes an efficient energy management system (EMS) for industrial microgrids (MGs). Many industries deploy large pumps for their processes. Oftentimes, such pumps are operated during hours of peak electricity prices. A lot of industries use a mix of captive generation and imported utility electricity to meet their energy requirements. The MG considered in this paper includes diesel generators, battery energy storage systems, renewable energy sources, flexible loads, and interruptible loads. Pump loads found in shipyard dry docks are modelled as exemplar flexible industrial loads. The proposed EMS has a two-stage architecture. An optimal MG scheduling problem including pump scheduling and curtailment of interruptible loads (ILs) is formulated and solved in the first stage. An optimal power flow problem is solved in the second stage to verify the feasibility of the MG schedule with the network constraints. An iterative procedure is used to coordinate the two EMS stages. Multiple case studies are used to demonstrate the utility of the proposed EMS. The case studies highlight the efficacy of load management strategies such as pump scheduling and curtailment of ILs in reducing the total electricity cost of the MG.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.5
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available