Factors Affecting Rework Costs in Construction

Journal

Publisher

ASCE-AMER SOC CIVIL ENGINEERS
DOI: 10.1061/(ASCE)CO.1943-7862.0001324

Keywords

Rework costs; Project characteristics; Construction; Regression model; Cost and schedule

Ask authors/readers for more resources

Rework adversely impacts the performance of building projects. In this study, data were analyzed from 788 construction incidents in 40 Spanish building projects to determine the effects of project and managerial characteristics on rework costs. Finally, regression analysis was used to understand the relationships among contributing factors and to develop a model for rework prediction. Interestingly, the rework prediction model showed that only the original contract value (OCV) and the project location in relation to the company's headquarters contributed to the regression model. Project type, type of organization, type of contract, and original contract duration (OCD), which represents the magnitude and complexity of a project, were represented by the OCV. This model for rework prediction based on original project conditions enables strategies to be put in place prior to the start of construction, to minimize uncertainties, to reduce impacts on project cost and schedule, and, thus, to improve productivity. (C) 2017 American Society of Civil Engineers.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.6
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available