A multivariate approach for top-down project control using earned value management

Journal

DECISION SUPPORT SYSTEMS
Volume 79, Issue -, Pages 65-76

Publisher

ELSEVIER
DOI: 10.1016/j.dss.2015.08.002

Keywords

Project management; Schedule control; Earned value management (EVM); Simulation; Principal component analysis (PCA)

Ask authors/readers for more resources

Project monitoring and the related decision to proceed to corrective action are crucial components of an integrated project management and control decision support system (DSS). Earned value management/earned schedule (EVM/ES) is a project control methodology that is typically applied for top-down project schedule control. However, traditional models do not correctly account for the multivariate nature of the EVM/ES measurement system. We therefore propose a multivariate model for EVM/ES, which implements a principal component analysis (PCA) on a simulated schedule control reference. During project progress, the real EVM/ES observations can then be projected onto these principal components. This allows for two new multivariate schedule control metrics (T-2 and SPE) to be calculated, which can be dynamically monitored on project control charts. Using a computational experiment, we show that these multivariate schedule control metrics lead to performance improvements and practical advantages in comparison with traditional univariate EVM/ES models. (C) 2015 Elsevier B.V. All rights reserved.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available