Journal
REGE-REVISTA DE GESTAO
Volume 27, Issue 1, Pages 2-20Publisher
EMERALD GROUP PUBLISHING LTD
DOI: 10.1108/REGE-02-2018-0026
Keywords
MRO; Project management; TOC; Aircraft maintenance; Critical chain project management; Critical path method
Categories
Ask authors/readers for more resources
Purpose - This paper aims to exemplify the use of project management tools in the scheduling of aircraft maintenance activities. This process is known as maintenance, repair and overhaul and it has gained importance within the aeronautical sector due to its expected growth in the coming years; however, it also faces increasing competitiveness in its market. This fact gives rise to the need of acting in maintenance management and seeking lower costs while maintaining the quality of the service provided. The purpose of this paper is to propose the structuring of a procedure that aims to reduce the total maintenance time (downtime) and guarantee the delivery of the aircraft on time. Design/methodology/approach - The paper, through a case study at a Brazilian aircraft maintenance center, used critical path method and critical chain project management, the latter being derived from the theory of constraints, with the purpose of analyzing resources systematically and synchronizing the activities in the precedence network. Findings - As a result, it is shown that downtime can be reduced from 11 to 5 days and improvements are proposed to achieve greater market competitiveness. Originality/value - This paper demonstrates the competitive advantage that resulted from the application of project management tools in the aircraft maintenance planning and execution.
Authors
I am an author on this paper
Click your name to claim this paper and add it to your profile.
Reviews
Recommended
No Data Available