Smart heuristics for decision-making in the 'wild': Navigating cost uncertainty in the construction of large-scale transport projects

Journal

PRODUCTION PLANNING & CONTROL
Volume -, Issue -, Pages -

Publisher

TAYLOR & FRANCIS LTD
DOI: 10.1080/09537287.2023.2248942

Keywords

Contingency; construction; heuristics; uncertainty; transport projects

Ask authors/readers for more resources

This article introduces a method for estimating cost contingency in large-scale transport projects called smart heuristics. Smart heuristics are simple decision strategies that are superior to statistical reasoning when dealing with uncertainty. The article sets forth a research agenda for building and using smart heuristics and identifies methodological considerations for adapting and discovering new heuristics in the contingency estimation process.
Statistical approaches such as Reference Class Forecasting and Monte Carlo Simulation are widely used to estimate the cost contingency of large-scale transport projects (>$500 million) to mitigate cost overruns during construction. Such approaches may accommodate exposure to risk, but they will fall short in the face of the irreducible uncertainty that confronts project delivery. An underused alternative for formulating a cost contingency is smart heuristics (i.e. simple task-specific decision strategies), which are superior to statistical reasoning under Knightian uncertainty. We set forth an agenda for research on building and using an 'adaptive toolbox' of ecologically rational heuristics that decision-makers can apply to produce more accurate contingency estimates for large-scale transport projects. We identify several methodological considerations to support the adaptation and discovery of new heuristics for decision-makers to navigate judgments under uncertainty during the contingency estimation process. The implications for research, policy, and practice are also identified. The contributions of our paper are twofold as we: (1) provide a platform for challenging the effectiveness of the prevailing convention of using statistical reasoning to estimate a project's cost uncertainty; and (2) identify an avenue for testing existing and discovering new heuristics that can assist decision-making in projects.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.5
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available