Robust identical parallel machine scheduling with two-stage time-of-use tariff and not-all-machine option

Journal

Publisher

TAYLOR & FRANCIS LTD
DOI: 10.1080/00207543.2023.2228922

Keywords

Energy-efficient scheduling; identical parallel machine; robust optimisation; memetic algorithm; min-max regret

Ask authors/readers for more resources

This study investigates the robust identical parallel machine scheduling problem with a two-stage TOU tariff and NAM option, aiming to improve energy efficiency in the manufacturing industry by regulating the electricity imbalance between supply and demand. The problem is formulated into a min-max regret model to maximize robustness, and both an iterative relaxation-based exact algorithm and a memetic differential evolution-based heuristic are developed to solve the problem. Computational experiments are conducted on randomly generated instances with up to 20 jobs and large-sized instances with up to 150 jobs to evaluate the performance of the developed methods and identify managerial insights for achieving energy-efficient schedules.
Time-of-use (TOU) tariff has been implemented in the manufacturing industry to improve energy efficiency by regulating the electricity imbalance between supply and demand. Besides, not-all-machine (NAM) option is another way of energy-saving by using only a subset of all the available machines. This study investigates a robust identical parallel machine scheduling problem with a two-stage TOU tariff and NAM option. Only interval bounds on job processing times are known. The problem is first formulated into a min-max regret model to maximise the robustness. Based on problem properties, both an iterative relaxation-based exact algorithm and a memetic differential evolution-based heuristic are developed to solve the problem. Computational experiments on 240 randomly generated instances with up to 20 jobs are conducted to evaluate the performance of the developed methods. Besides, 900 large-sized randomly generated instances with up to 150 jobs are tested for sensitivity analysis and to identify managerial insights for achieving energy-efficient schedules.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available