Peak load minimization in smart grid by optimal coordinated ON-OFF scheduling of air conditioning compressors

Journal

SUSTAINABLE ENERGY GRIDS & NETWORKS
Volume 28, Issue -, Pages -

Publisher

ELSEVIER
DOI: 10.1016/j.segan.2021.100545

Keywords

Air conditioning system; Dead-band temperature; Smart grid; Load scheduling; Optimization; Mixed integer linear programming; Heuristic algorithm; Power consumption

Ask authors/readers for more resources

This study focuses on minimizing peak load by optimizing coordinated ON-OFF scheduling of air conditioner compressors in a smart grid. Both optimal and heuristic approaches significantly reduce peak load and load variance, albeit with a slight increase in energy consumption. The heuristic algorithm proves to be more efficient in computational time, especially for a large number of air conditioning systems.
We address the problem of minimizing the peak load by optimal coordinated ON-OFF scheduling of the compressors of air conditioners (ACs) connected in a smart grid. For this purpose, we consider a simplified model of power consumption profile, i.e., on-time and off-time durations and power consumption values of a split type AC. We model the necessary constraints and formulate an optimization problem to minimize the peak load by optimal coordinated ON-OFF scheduling of the AC compressors. The optimization problem is found to be a complex mixed integer linear programming problem. We optimally solve the problem for a small number of ACs by using an optimization tool. Unfortunately, due to the computational complexity, the tool cannot solve the problem for a large number of ACs. For a large number of ACs, we develop a heuristic algorithm to solve the problem. Using the optimization tool and the heuristic algorithm, we determine the peak load, load variance, and energy consumption in operating a number of ACs and compare them with the results obtained for a traditional non-coordinated AC operation. We find that both the optimal and heuristic solution approaches significantly reduce the peak load and load variance with some increment of energy consumption. Further, the computation time of the scheduling of the AC compressors of an air conditioning system under the heuristic algorithm is found to be significantly less compared to the time bound on scheduling computation of the AC compressors even when the number of ACs in the system is large. (C) 2021 Elsevier Ltd. All rights reserved.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available