Automated scheduling and control of mechanical and electrical works with BIM

Journal

AUTOMATION IN CONSTRUCTION
Volume 124, Issue -, Pages -

Publisher

ELSEVIER
DOI: 10.1016/j.autcon.2021.103600

Keywords

BIM; Scheduling; Mechanical and electrical works; Automation; Optimization

Ask authors/readers for more resources

This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works, utilizing topological analysis of component position to define relationships between installation tasks and determine the optimal schedule. Specific control points are defined to support effective progress tracking, ensuring tasks adhere to the schedule in practice.
Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be used for more detailed and accurate planning of their installation, and to identify points where work progress should be tracked. This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works. A topological analysis of the precise position of components is used to define relationships between the installation tasks, and to identify the optimal schedule. The definition of specific control points supports effective progress tracking to ensure that tasks adhere in practice to this schedule.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available