4.5 Article

The Development of Dewatering Predictions of the Velenje Coalmine

Journal

ENERGIES
Volume 9, Issue 9, Pages -

Publisher

MDPI
DOI: 10.3390/en9090702

Keywords

colliery; coal mine; excavation; pumping; dewatering; predicted dewatering; groundwater; aquifer

Categories

Funding

  1. Slovenian Research Agency (ARRS) [L1-5451]
  2. Velenje coalmine

Ask authors/readers for more resources

The complex hydro-geological situation, particularly in terms of groundwater, has been a constant threat to the mining carried out at the Velenje colliery since its inception. Of particular interest to the authors are the difficulties presented to the colliery by the adjacent sand aquifers, as the water pressure within these sands directly impacts mining safety, and the aquifers themselves are most directly affected by dewatering. In order to monitor water levels and estimate dewatering at the Velenje wells, multi-layered modelling using 3D Finite Difference Method (FDM) has already been carried out. However, FDM is not optimal due to its greater dependence on cell size than on water flow. In 2017 in Velenje, a series of wells will be terminated as a result of mining and mining-induced subsidence, leading to dewatering and danger of flooding. As part of a plan to address this by replacing dewatering structures, a series of drive-in filters will be implemented around the entry and exit point tunnels of a longwall face. Because FDM seems to be inadequate for purposes of optimising this process, the Finite Elements Method (FEM) was applied in this case. Based on such an application of FEM, a prediction of the optimisation of drive-in filters was carried out by the authors.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.5
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available