Excavation of the Aica-Mules pilot tunnel for the Brenner base tunnel: information gained on water inflows in tunnels in granitic massifs

Journal

ROCK MECHANICS AND ROCK ENGINEERING
Volume 47, Issue 3, Pages 1049-1071

Publisher

SPRINGER WIEN
DOI: 10.1007/s00603-013-0480-x

Keywords

Tunnels inflows; Hydrogeology; Granitic rocks; Permeability; Groundwater flow

Ask authors/readers for more resources

The construction of the Aica-Mules tunnel, completed in 2010, provides a relevant case history for improving the knowledge of hydrogeological issues related to the excavation of deep tunnels in granitic massifs. The Aica-Mules tunnel is a 10 km-long structure, forming part of the high-speed railway connection between Austria and Italy across the Alpine chain, located at an average depth of 500-1,000 m below the surface. Prior to and during the construction, intense hydrogeological monitoring was set up, allowing the collection of abundant data concerning: (1) the evolution of water inflows into the tunnel; (2) the chemistry and temperature of drained groundwater; and (3) the influence of tunnel drainage on springs. Based on detailed analysis of geological/hydrogeological data, this article provides an insight into the permeability distribution in granitic rocks affected by relevant brittle tectonic deformation, and the consequences of water inflow during excavation. The available time series from the principal water discharges in the tunnel have been used in order to test the reliability of some of the most commonly applied analytical methods for the forecast of water inflows into tunnels.

Authors

I am an author on this paper
Click your name to claim this paper and add it to your profile.

Reviews

Primary Rating

4.7
Not enough ratings

Secondary Ratings

Novelty
-
Significance
-
Scientific rigor
-
Rate this paper

Recommended

No Data Available
No Data Available