APPLIED ENERGY
Volume 144, Issue -, Pages 96-105Publisher
ELSEVIER SCI LTD
DOI: 10.1016/j.apenergy.2015.01.043
Keywords
Cost benefit analysis; Distributed generation; Interruptible connections (non-firm); Smart solutions
Categories
Funding
- UK Power Networks via the Low Carbon Networks Fund's Flexible Plug and Play Project
Ask authors/readers for more resources
The aim of this study is to quantify the trade-off between selecting a distributed generation (DG) smarter connection with limited export capacity and a more expensive firm DG connection with a guarantee of full export capacity. The study is part of the analysis of a customer funded network innovation project in the UK. A cost-benefit analysis of the different connection options for connecting DG customers in a specific constrained area in the UK is performed. The study not only requires the identification of the main cost drivers and revenues (including embedded benefits and those allowed by regulation) for getting a new DG connection but also illustrates the interaction (operational and contractual) between the different parties involved (generators, distribution network operators, electricity suppliers, and demand). This study provides empirical evidence, under a number of scenarios, of the potential savings when a smart connection option is available. The results suggest that in general small wind DG customers will always have an advantage in selecting a smarter connection over large ones. We also examine the type of connection that would be preferred by solar PV DG customers and Anaerobic Digestion (AD) DG customers. The study shows that lower curtailment levels tend to substantially reduce the value of firm connections. (C) 2015 Elsevier Ltd. All rights reserved.
Authors
I am an author on this paper
Click your name to claim this paper and add it to your profile.
Reviews
Recommended
No Data Available